When does the delay start costing, and when should the fix be in service?
Everything that burns money for every day the fix isn't in service. Change any number and the meter recalculates.
| Cost line | Type | Qty | £ per unit/day | £/day | Funded |
|---|
Log any day that hurt the project. Assets out are priced at the rate above.
| Date | What happened | Trains out | Other £ | Day cost |
|---|
Use codes instead of real names in the template. The real names, and any scale factor that hides the true figures, sit in your key. The key stays on this computer and is never saved with the project or shared.
The money allocated to the project. The countdown spends it at the daily rate of every cost line ticked “Funded”, plus extra daily costs from changes.
No baseline yet. Set one to track how the project moves.
| Capital cost of the fix | |
| Changes: one-off costs | £0 |
| Delay cost to date | £0 |
| Bad days logged | £0 |
| Further delay cost to revised target | £0 |
| Total if delivered on revised target | £0 |
What obsolescence costs the depot while it waits for the fix. These costs stop when the fix is in service, so delay makes them bigger.
Daily burn by type.
Drag to bring the in-service date forward or push it back.
Anything found along the way, such as new scope, a design change or a supplier slip. Give each one a one-off cost, any extra daily cost and the days it adds to the timeline. Untick an item to see the project without it.
| Found | Change | Type | One-off £ | Extra £/day | Delay days | Paid by | Growth %/month | Include | Total impact |
|---|
Total impact = one-off cost + the extra daily cost from the date found until the fix is in service (growing at its monthly rate) + the delay days charged at the full cost of being late. “Paid by Depot” keeps a cost out of the project funding but in the project’s total impact.
The supplier is paid in stages. Each gate’s payment is held until the gate is passed, then the money is released. Held money still counts as committed against the funding, and the countdown pays each gate on its planned date.
| Gate | Payment £ | Planned date | Status | Date passed | Timing |
|---|
Failed a gate? Set it to “Failed: re-review”, move the planned date, and add the slip as a change so the target date moves too.
This is a made-up sample project (Northbridge Rail). Download a template to track your own.